Core Installation Steps for Bailey Steel Bridges

Nov 24, 2026

Leave a message

The construction sequence generally follows the order of "transverse members first, then longitudinal members, and finally deck panels," as detailed below:
Install transverse distribution beams: This is the first step in setting up the bridge. The transverse distribution beams are lifted and positioned above the upper chords of the Bailey beams at the design spacing, and secured with special connectors (see below for details).
Install longitudinal distribution beams: On the fixed transverse distribution beams, longitudinal distribution beams or wooden battens are laid at the design spacing and connected to the transverse distribution beams.
Lay the bridge deck panels: The bridge deck panels (such as checkered steel plates) are laid on the longitudinal or transverse distribution beams. Expansion joints of 5–30 mm are left between panels in accordance with specifications to accommodate temperature changes and facilitate installation.
Secure the bridge deck panels: The deck panels are firmly connected to the distribution beams below using bolts, clips, welding, or other methods.
Install auxiliary structures: After the deck panels are laid, safety protection facilities such as guardrails, toe boards, and anti-slip strips are installed.