Installation Of Bailey Beam

Nov 04, 2020

Leave a message

Firstly, you can connect the grouping bailey beam assembled on the ground. Mark the bailey beam position with red paint at the required intervals on the i-beams across the bridge. Use the car crane to lift the connected bailey beam into place in the order of first middle and then both sides. Two lifting points must be set up in the hoisting process of single-row Bailey beam and distributed equidistant to keep the balance of Bailey beam in the hoisting process, so as to avoid the distortion stress in the hoisting process. After all the Bailey beams are erected, 14 I-beams shall be set every 100cm as the distribution beam, and then 12×12cm square timber shall be set every 30cm from the longitudinal bridge on the I-beams distribution beam.