A. After the entry of bailey tablets, they shall be stacked in the leveled site; bailey panel shall be assembled outside the construction site. Before assembling, carefully check whether there is any damage or damage to each component. It is forbidden to use if there is any.


B. Put 10*10cm square wood at the assembly node of bailey beam, the spacing between square wood and the name node of the side beam is the same, two square wood are placed side by side at each node, and the leveling is carried out with the level, the height of square wood is the same, the deviation is controlled within 3mm.


C. In order to ensure the overall stress and structural performance of the bailey beam system, the upper and lower of the single-phase bailey beam must be vertical and the upper and lower of each rod bailey beam must be parallel to each other, and there must be no inclination or distortion, etc. The top surface of the bailey beam installed must be on the same plane, and there must be no wrong platform.


D. Check the axis and level of the assembled military beam, and transport it to the site for installation after the assembling error meets the requirements of the specification.


E. Before formal use, the assembly size, bailey bolts and bailey pins shall be thoroughly checked to ensure that they are installed in place.