Construction method for reinforcement preparation of bailey steel bridge

Mar 28, 2024

Leave a message

The goal of strengthening the steel bridge project is to achieve repair, strengthening, improving the bearing capacity and strengthening the utilization function through the reinforcement construction process, so that the selection of the reinforcement plan should be based on the improvement of the quality of the reinforcement project. There are also different construction preparation and quality evaluation criteria for the unsuitable reinforcement schemes. According to several typical reinforcement preparations in the "Technical Specifications for Concrete Layout reinforcement" and following construction experience, unsuitable reinforcement preparations should be focused on:

1, prestressed reinforcement method
When prestressed tie rod reinforcement is adopted, the tie rod must be straightened before installation, the size and installation position of the tie rod must be accurate, and the quality of the welded joint, screw and nut should be checked before tensioning. The quality of the embedment depth of the force transfer weld between the Angle steel (and its support plate) at the end of the strut rod should be checked. Both ends of the support rod are fixed with bolts, and then filled with epoxy sand slurry or high-strength cement sand slurry. The reinforced pressure rod limbs, connecting plates, fixing plates and tension bolts should be coated with anti-rust paint for anti-corrosion.
2, steel reinforcement method
bailey steel bridge should be placed in the general situation, including the coagulated connecting surface and the steel plate lamination surface, as the key point in the reinforcement construction process. For the dry reinforcement construction, in order to make the Angle steel close to the general situation of the member, the concrete situation must be polished and smooth, without debris and dust; When wet reinforcement construction is adopted, latex cement slurry or epoxy resin chemical grouting material should be applied to the prepared Angle steel and concrete profiles, rust removal of steel plates, dust removal of concrete and cleaning steel plates and concrete profiles with acetone or xylene, and bonding and irrigation.
3, concrete members external bonding steel reinforcement method
The construction of this method is relatively simple, but the first need to focus on the general treatment of concrete and steel plates, the adhesive surface of old and dirty concrete members, clean to dust, and then rub the situation with acetone; The general processing of the steel plate should be in accordance with its embroidery environment, sandblasting, emery cloth, grinder grinding, so that the steel plate appears metallic luster, grinding lines as far as possible and the target perpendicular to the force, and then rub with acetone clean. Secondly, we must hope for the choice of adhesives, the current domestic market building layout adhesive fish dragon thick turbid, the choice of adhesives must be careful. The third is to rely on the details in the process of gluing and pasting, the adhesive should strictly follow the proportion of the declaration requirements, especially to control the dosage of curing agent, stirring to be average, and at the same time, it is necessary to guarantee the fullness and density of the paste surface when pasting. Finally, it is hoped that there will be no disturbance to the steel plate during the curing stage.