Simple process for preloading of bailey plate truss

Oct 16, 2023

Leave a message

After the erection of the truss is completed and the joint acceptance of all departments, the truss is preloaded to reduce the influence of inelastic deformation. According to the design drawings, the preloaded load is 1.1 times of the total load weight. Water tank filling ballast was used in static load test.

Bailey truss load test monitoring monitoring method:

1. Determine the level observation point, install the level.

2. The bridge load deflection value is measured and recorded at three points (front, middle and back) of the Beret truss.

3. The use of water tank ballast, ballast weight is 1.1 times of the total load weight. The bridge load deflection at three points was measured and recorded.

4. According to the code, check whether the bridge load deflection is qualified.