Technical requirements of bailey bridge erection points

Jan 27, 2021

Leave a message

1. When a single-span bridge is erected, the horizontal distance between the piles of Angle of repose on both sides should generally be less than 3-4 meters in bridge span.


2. The soil at the bridge seat on both sides should be solid. When the soil pressure cannot reach the design requirements, the foundation under the bridge seat plate must be expanded or strengthened.


3. The height difference between the two sides should not be greater than 5% of the bridge span.


4. When using the cantilever push-pull method to erect the bridge, the bank shall have the equipment configuration and assembly site with the length not less than 1.5 times of the bridge span and the width of 8 ~ 14 meters. The length of the site should not be less than the span of the bridge when the local shape is limited and the erection method is needed by side assembly and side push.


5. The longitudinal slope of the assembly site should be no more than 3%, and the transverse slope should be roughly level.