Construction Method Of Bridge Bailey Frame

Jul 22, 2024

Leave a message

The construction method of bridge Bailey frame mainly includes three stages: installation, use and demolition.

Installation phase:

Integral installation method: When the space and lifting weight meet the requirements, Bailey architecture parts are assembled into pieces, and the hoisting equipment such as tower crane is used to lift the whole to the installation point.
Segmented installation method: In the case that the lifting weight does not allow the whole lifting, bailey frame of the span section of the hole is installed first, and then the whole is connected at both ends.
Translation installation method: After the whole section is assembled, the Beret frame is simultaneously translated to the installation point using forklift and other equipment at both ends.
Use stage:

In the process of use, the bailey frame as the main load-bearing structure is used to support the superstructure of the bridge to ensure the safety and stability of the structure during the construction process.
Demolition stage:

Translation removal method: The bailey frame is synchronously moved to the nearby floor by forklift and other equipment, and then dismantled into scattered components.
Traction demolition method: the hanging hole is reserved during construction, and the hanging hole and tractor are used to move the bailey frame to the floor when dismantling it.