Daily Erection Process Of Bailey Steel Bridge

Mar 24, 2025

Leave a message

Assemble bridge sections
On the flat ground at the shore, assemble the truss pieces into standard sections (usually 3 meters per section) using connecting pins.
Install the crossbeams and bridge deck to form stable unit modules.

Pushing and erection
Cantilever pushing method (commonly used):
Install rockers (rolling support devices) and guide beams at the abutment.
Gradually push the assembled bridge sections forward, with cranes or manual assistance at the rear.
After each section is pushed out, use temporary supports to fix it to prevent overturning.
Lifting method: If conditions permit, use cranes to directly lift and install pre-assembled bridge sections.
Connection and fixation
After the bridge reaches the opposite bank, adjust its position and seat it on the abutment.
Install the end cross beams, bridge decks, and fix all connection pins and bolts.

Reinforcement and Testing
Install wind-resistant tie rods, diagonal braces and other reinforcing structures.
Conduct load testing: gradually increase the weight (such as sandbags or vehicles), and check for deformation and stability.